John Day Lock & Dam - Spillway Flow Deflector

U.S. Army Corps of Engineers | Columbia River, Oregon | Heavy Civil Infrastructure / Dam Modification
John Day Lock and Dam dewatering operations

Project Overview

Glen/Mar performed major modifications to Spillbay 20 at John Day Lock & Dam, including dewatering the spillbay approximately 55 feet, diving operations, concrete demolition, structural anchoring and fabrication and installation of a new flow deflector.

The work included approximately 1,500 cubic yards of new ogee concrete, barge-crane and floating-plant operations, removal and replacement of dam components, and relocation and installation of a 45-ton Top Spillway Weir. Construction was coordinated around ongoing dam operations and the requirements of multiple agencies and stakeholders working within the Columbia River system.

CLIENTU.S. Army Corps of Engineers
LOCATIONColumbia River, Oregon
PROJECT TYPEHeavy Civil Infrastructure
CONTRACT VALUE$2.50M
COMPLETIONApril 2010
SCOPESpillway Flow Deflector Modification
John Day Lock and Dam completed spillway flow deflector work
Construction inside an operating federal dam. The project required deep dewatering, heavy lifting, diving, floating plant and concrete work in a tightly controlled spillway environment.